基於上一個Post有人留言想我用例子講解, 所以我呢個Post就講下點Size一部消防Genset. Size一部Genset既時候, 我會有以下既次序:

Step 1: 列曬所有要消防發電機Backup既Load

LoadPower FactorSteady kWSteady kVAStarting MethodCurrent MultiplierStarting kWStarting kVA
Emergency Lighting0.95050/0.9=55.615055.6
Sprinkler Pump 0.857575/0.85=88.24S/D2.5187.5220.59
FH/HR Pump0.855555/0.85=64.7S/D2.5137.5161.75
Firemen’s Lift0.858585/0.85=100VVVF1.7144.5170
Sprinkler Intermediate
Booster Pump
0.854545/0.85=52.9S/D2.5112.5132.25
Street Fire Hydrant
Pump
0.85132132/0.85=155.3S/D2.5330388.2

上面係簡單既例子, 你要因應你個Project有既Load做翻一個類似既Table (其他FS Load例子包括有: Smoke Extraction, Staircase pressurization…等等). 當你做好左個Table之後, 其實你已經大概知道你部Genset要幾多kVA(kW)了, 原因係你要Fulfil到Genset Rating in kVA > Total Steady kVA 同 Genset Rating in KW > Total Steady kW 呢兩個條件. 所以, 你做完呢個Table之後, 你就可以加曬所有Load既Steady kVA 同 Steady kW:

Steady load kVA in total 516.74 kVA
Steady load kW in total442 kW

就咁睇, 其實可以初步知道部Genset Rating最少會係大概600kVA – 700 kVA呢個Range, 因爲Genset本身有個0.8 power factor, 所以600 kVA既Genset其實就係等於512 kW. 550 kVA已經唔夠, 因爲Minimum 係550kVA x 0.8 = 440 kW.

為左呢個例子, 我去左Cummins (Genset Supplier)既網站揾左佢既Genset Model, 最近600 kVA有C700 D5 (640 kVA). 但其實呢部Genset係會唔夠大, 我自己係會選擇大三級既C1000 D5(939kVA/751kW)發電機, 主要原因係滿足唔到Step Load要求. 咁呢個例子我地既選擇就係C1000 D5呢部發電機.

Step 2: 分Step去滿足發電機60% Step Load Acceptance要求

之前講左, 每部發電機都有個Step Load Acceptance既Percentage. 我地Design階段無辦法知道將來會用邊部機, 所以我地通常都係Take Minimum, 姐係60%. 以我地選擇左既C700 D5為例, 每個Step最多可以頂到既就係 751 x 0.6 = 450.6 kW.

如果消防發電機, 我自己普遍最多分2-3個Step, 主要我唔知道各類型Equipment個Starting time係幾多. 但我有個宗旨就係將唔係電池Backup既消防燈放第一個Step, 因爲我要確保佢可以跟到消防例, 5秒起到. 但係當然, 呢家好多Project都係用CBS/電池Backup, 所以消防燈變相可以放係最後個Step. 呢個例子, 我地就Assume消防燈係有CBS/電池Backup, 我地會將Essential Lighting呢個Load放係最後.

重點黎了, 就係點樣將上面既Load分Step. 我地要確保每個Step既Starting kW加埋唔可以大過450.6 kW, 同時要確保消防發電機個15秒要起到大部分既Load (因爲消防官試Genset都同一時間可以睇到係咪所有Equipment係15秒内有後備電源, 所以要有策略咁放一啲消防官一定會第一時間驗既Load係第一個Step). 我自己就會好似下面咁分:

Step 1:Starting kWStarting kVASteady kWSteady kVA
Street Fire Hydrant Pump330388.2132155.3
Sprinkler Intermediate Booster Pump112.5132.254552.9
Total:442.5 < 450.6 kW520.45177208.2
Step 2:
FH/HR Pump137.5 161.755564.7
Sprinkler Pump187.5220.597588.24
Total:325 < 450.6 kW382.34130152.94
Step 3:
Firemen’s Lift144.517085100
Emergency Lighting5055.65055.6
Total: 194.5 < 450.6 kW225.6135155.6

睇翻上面個Table, 其實可以判斷到如果部Genset細啲, 就會有2個情況出現: 1. 分好多個Step, 有機會好耐都未起曬啲Load. 2. Step Load Acceptance本身個Load細到有機會頂唔到某啲Load (呢個例子Street Fire Hydrant = 330 kW, 330/0.6 = 550 kW, 姐係部Genset Min.都要550 kW先食到Street Fire Hydrant個Starting Current).

Step 3: Check埋餘下既Requirements (Volt Dip, Genset 10% Overload)

基於Voltage Dip條Curve要問Supplier先有, 我揾到另一份1000 kVA Genset Alternator既Voltage Dip Curve做例子:

Check Voltage Dip就係攞Starting kVA最大既Step然後督落條380V 條 Curve就得. 我地呢個例子的話, Step 1係最大 (442.5 kW / 520.45 kVA). 對應翻條Curve, 520.45 kVA應該係大概9.5% Volt Dip. 由於細過20%, 所以Volt Dip OK.

最後, Check埋Genset個Overload Capacity. 呢個個計法就係Step 1 Steady kW + Step 2 Steady kW + Step 3 Transient kW. 以呢個例子, 個總數應該係: 177 + 130 + 194.5 = 501.2. 而Genset個10% Overshoot係Genset Rating x 1.1, 所以C1000 D5 (751 kW) 既Overshoot係751 x 1.1 = 826.1 kW. 由於501.2 kW < 826.1 kW, 所以都係滿足到Genset Overload呢個要求.

結論:

當然, 滿足曬呢啲要求就知道部Genset夠比呢堆Load, 但其實做Genset Design要計埋油缸同Louvre, 呢2個Topic我會遲啲再出Post解釋下. 所以記得Subscribe呢個Blog, 咁你就唔會錯過我出既Post, 同埋記得Share埋比你既同學仔/同事, 下個Post見~